Market Demand Assessment for Incremental Capacity 2025

15 July 2025

In accordance with the incremental capacity process as described by NC CAM (Regulation 2017/459), interested parties are invited to submit non-binding demand indications for capacity above the current technical capacity of the BBL interconnector, using BBLC’s request form as published below. Requests can be submitted during a window period of 6 weeks, starting from the date of this publication.

The key dates for this market demand assessment are as follows:

ActivityDate
Expression of interest for Market Demand Indications document published15 July 2025
Market Demand Indication window openDuration 6 weeks
Market Demand Indication window closes26  August 2025
Market Demand Assessment Report publishedNo later than 27 October 2025

Latest news

24 August 2026

BBL Pipeline celebrates 20 years of connecting the Netherlands and Great Britian with public Open Day in Anna Paulowna

The installation in Anna Paulowna, which has served as an important link in the energy connection between the Netherlands and Great Britain for the past twenty years, will open its doors to the public on Saturday, 26 September. Visitors will have a unique opportunity to take a look behind the scenes at a site that is normally not accessible to the public. It is here that the 235-kilometre gas pipeline beneath the North Sea connects the two countries.

Read more Arrow right icon

2 July 2026

BBLC tariffs for gas year 2026 and beyond

BBL Company has published its tariffs for gas year 2026 and beyond . These apply to Forward Flow (NL to GB) and Reverse Flow (GB to NL) capacity products offered through PRISMA and the Implicit Allocation mechanism.

Read more Arrow right icon

1 July 2026

Tullett Prebon joins the BBLC IAM Platform

BBL Company (BBLC) is pleased to announce that Tullett Prebon is now available as the fourth broker connected to the BBLC Implicit Allocation Mechanism (IAM) platform.

Read more Arrow right icon