In accordance with the European regulation NC CAM (EU) 2017/459 interested parties may submit non-binding demand indications for interconnection points for a window period of 8 weeks, starting from the day that the annual yearly auction opens.
Therefore BBLC will publish on July 5th to all interested parties an demand indication document in order to facilitate the submission of market demand indication requirements for incremental capacity at IP Bacton. The publication will be published on July 5th on our website.
The key dates for this market demand assessment process are as follows:
| Activity | Date |
|---|---|
| Publication of market demand indication document | 5 July 2021 |
| Market demand indication window open | 8 weeks |
| Market demand indication window closed | 30 August 2021 |
| Market demand assessment report publishes | No later than 25 October 2021 |
Latest news
27 October 2026
BBL physical flow switch to Forward Flow 28/10/2026
The BBL physical flow direction is currently in Reverse Flow mode (GB to NL). BBLC will switch the physical flow direction to Forward Flow (NL to GB) starting gas day 28 October 2026 06:00 CET and is anticipated to be finalized by 29 October 2026 06:00 CET.
19 October 2026
Transition to winter time 2026
On gas day 24 October 2026 there will be a switch from summer time to winter time. This means that this gas day will have 25 hours.
7 October 2026
BBL Company launches new Capacity Overview Dashboard
BBL Company (BBLC) has launched a new Capacity Overview Dashboard on its website, providing market participants with easy access to capacity information through a modern and interactive reporting tool.