Planned maintenance 2019 (update)

On 1 October 2018 BBLC has informed the market that maintenance activities were planned to take place in the month of September 2019.  

On 1 November 2018 BBLC has informed the market that its physical reverse flow project likely would be ready three months earlier than announced and that related construction works would take place in May and June 2019, this period to be confirmed when a more detailed planning would be available.

BBLC now can confirm that the planned maintenance activities will be incorporated in the mentioned May and June 2019 period and will take place from 15 May 2019 through 29 May 2019. 

From 30 May 2019 through 30 June 2019 physical reverse flow construction works and commissioning activities will take place. 

During the whole period (15 May – 30 June) no BBL transmission capacity will be available.