More details on planned BBL maintenance in September 2011

-

Several months ago BBL Company has communicated via its website that planned maintenance will be carried out in the first half of September 2011. More information is now available about the exact timing and the level of available capacity.

It is anticipated that the maintenance work will be carried out from gas day Monday 12 September 2011 up to and including gas day Wednesday 14 September 2011. There will be no gas flows for the whole maintenance period.

The work will start on Monday 12 September 2011 at 07:00 LET. At 07:00 LET on Thursday 15 September 2011, the work is expected to be finished and the gas flow will be resumed.