Maintenance Programme update II

The planned maintenance activities combined with physical reverse flow construction works and commissioning are still proceeding as planned. Forward flow commissioning is currently planned to be ready on 23 June 2019 and reverse flow commissioning on 27 June 2019, which allows some slack until 1 July 2019 for last minute adjustments.

Due to reverse flow IT and regulatory topics not being finalized in time for the upcoming Yearly auction BBLC will only offer forward flow capacity on the Prisma platform 1 July 2019.